Excavation example sentences
Related (9): archaeology, digging, site, artifacts, trenches, survey, earthmoving, burials, paleontology
"Excavation" Example Sentences
Common Phrases
- The archaeological excavation unearthed many ancient artifacts.
- The project required several months of excavation and digging.
- The team carefully mapped and documented each stage of the excavation.
- Excavation work has been ongoing at the construction site all week.
- During the excavation, the construction crew must properly dispose of the excess dirt.
- The proper safety equipment was required during the sewer excavation project.
- The basement excavation required several tons of dirt to be removed.
- Modern machinery was used to speed up the road excavation work.
- They had to shore up the walls of the excavation with timber beams.
- Silt screens were erected around the pond excavation area.
- The huge trench excavation was a massive undertaking.
- Workers entered the tunnel excavation after it had been properly ventilated.
- Groundwater pumping was necessary during the canal excavation.
- The archaeological excavation may yield new information on the lost civilization.
- The team leader planned out the phases of the excavation in advance.
- Hand tools were used for delicate portions of the artifact excavation.
- Ground-penetrating radar was used before the foundation excavation began.
- Steel strapping was used to reinforce the walls of the deep excavation.
- They were excavating a site that had been occupied for thousands of years.
- The cellar excavation took longer than expected due to unstable soil conditions.
- Shoring was installed around the building foundation excavation for safety.
- An excavator tracked vehicle was used for initial ground excavation.
- The footings were poured after the basement excavation was completed.
- An access road was built to reach the remote cave excavation site.
- The Indian burial site excavation yielded human remains and artifacts.
- The open pit mine excavation required ongoing reinforcement.
- The team examined the layers uncovered during the landfill excavation.
- They installed electric lines and pipes before backfilling the utility trench excavation.
- Several natural gas lines had to be relocated during the roadway excavation.
- The tunnel excavation was sealed off to keep out construction dust and debris.
- The group documented the stratified layers found in the ditch excavation.
- The shaft excavation was creating vibrations in the nearby structures.
- The basement excavation crew had to pump out several feet of groundwater.
- Careful excavation of the sculpture's foundation preserved its ancient carvings.
- Rock blasting was required for part of the channel excavation work.
- A twelve-foot section of sewer pipe was uncovered during the street excavation.
- The company owner monitored progress of the well excavation site.
- The deep pond excavation filled with groundwater within hours.
- The levee excavation work was put on hold due to heavy rains.
- They screened the dirt scooped out during the foundation excavation.
- The team stabilized the eroded walls of the pit excavation.
- The trench excavation filled with muddy rainwater overnight.
- Bracing was used around the walls of the pipe trench excavation.
- Several construction workers were injured during the building excavation project.
- The ancient well excavation yielded valuable historical artifacts.
- Asbestos removal was required before the patio excavation could proceed.
- The ditch excavation had to be dug several feet deeper at the last minute.
- Margins of error were built in to the excavation measurements and plans.
- The hot humid conditions slowed progress of the mine shaft excavation.
- Several artifacts from the indigenous culture were found during the marsh excavation.
- Heavy machinery was needed for constructing the large quarry excavation.
- Wattle fencing was used around the perimeter of the gravesite excavation.
- No ancient burials were uncovered during the construction excavation.
- The road realignment required several large culvert excavations.
- Archaeologists carefully backfilled theLATEST truncation error in excavation.
- The urban excavation was monitored by both environmental and historical agencies.
- The stone foundation of the old building was uncovered during the courtyard excavation.
- The narrowness of the pit excavation made safety challenges.
- Changes were requested to the plans for the subway tunnel excavation.
- Workers inundated the reservoirs formed from their pond excavation.